Work has been marginally delayed by rain, but work continues to progress on the 100th Street Rehabilitation Project from 14th to 20th Avenue, says the City of North Battleford.
traffic cone

Work has been marginally delayed by rain, but work continues to progress on the 100th Street Rehabilitation Project from 14th to 20th Avenue, says the City of North Battleford.

Power line trenching and street light installation has been completed on the 1400 block. Cleanup work will be completed on the 1400 block early this week and this block will be re-opened to traffic.

Temporary water supplies on the 1500 block will be disconnected and Precautionary Boil Water Advisories will be lifted once the required water sampling and testing has passed. Deep road patching on the 1500 block has begun, but has been delayed by rain. Sidewalk repairs will begin on the 1500 block, and top-lift paving will follow on the 1400 and 1500 blocks.

Sewer and water spot repairs are scheduled for the intersection of 16th Avenue and 100th Street, and will continue northward along the 1600 block. This will result in road closures and detours affecting the 1600 block.

Preparations will be made for temporary water supplies on the 1700 block, and water main replacement is scheduled to begin on that block the following week.

Businesses in the affected areas are accessible from the avenues and back alleys. Dairy Queen will be accessible from 100th Street and 17th Avenue southbound as well as the alley for Miracle Treat Day on Thursday, Aug. 13.

The City urges motorists to use caution when traveling through the work zones, and respect the safety of workers. Motorists should also be reminded to use caution, and respect the residents when traveling along detour routes.