100th Street rehabilitation week four

Project on schedule
traffic cone

Work is progressing as scheduled for the 100th Street rehabilitation project from 14th to 20th Avenue, according to a City of North Battleford press release.

This week underground replacement work will continue at the intersection of 16th Avenue and 100th Street. Street light and buried power line work will be happening on the 1400, and 1500 blocks, and roadway reconstruction and patching will begin on the 1500 block.

Work will also begin to prepare the new water main on the 1500 block for use, but temporary water supplies are expected to remain for next week.

Motorists can expect the 1500 block of 100th Street to remain closed for the week, and temporary lane or road closures on the 1400 block may be in effect as buried power line work progresses, the City says.

Businesses on the 1500 block are accessible from 15th and 16th Avenues, or from the back alley.

The City reminds motorists to use caution when travelling through the work zones for the safety of workers. Motorists are also reminded to use caution and respect residents when travelling along detour routes.