Infrastructure repairs in progress
city hall pic

The City of North Battleford has issued an update on work being done through the Underground Pipes and Roads (UPAR) program so far in 2016.

108th Street – 10th to 11th Avenue:  Underground utility work is complete, and the granular roadway structure is in place with the street partially open to traffic. Concrete curb and sidewalk repairs will start in the coming weeks and paving is to follow. Businesses and residents will be impacted by precautionary drinking water advisories as the water mains are brought into service.

St. Laurent Drive: Buried utility work begins early in the week between Douglas Avenue and Thompson Crescent. Businesses and residents in the area can expect water service disruptions, PDWA’s and access disruptions as work is completed through the week. Excavations will be graveled and the road will reopen to traffic once underground work is completed. Final paving is planned for later this summer. Work on the block was delayed approximately one week while preparations were made to take important water mains out of service during repairs.

95th Street: Underground utility work is complete. Final paving is planned for later this summer.

102nd Street, 16th to 17th Avenue: The City is urging caution when travelling through work zones and to respect the safety of workers.